CERC granted 45-day extension to Khaba Renewable Energy for 38.1 MW of 250 MW solar project in Barmer, Rajasthan, September 25, 2026, condoning six-day delay. Project under NHPC PPA April 18, 2024; 200 MW commissioned with certificates March 14, 27, June 26. 221 MW tranche got FTC March 2; NRLDC gave 45 days plus three months till July 15 exhausting limit under IEGC Regulation 19(3)(a).