• Infographics
  • Insights
  • Check Pricing
  • Newsletter
  • Login
September 28,2026

CERC Grants 45-Day Extension for Khaba's 38.1 MW Solar Project in Rajasthan

CERC granted 45-day extension to Khaba Renewable Energy for 38.1 MW of 250 MW solar project in Barmer, Rajasthan, September 25, 2026, condoning six-day delay. Project under NHPC PPA April 18, 2024; 200 MW commissioned with certificates March 14, 27, June 26. 221 MW tranche got FTC March 2; NRLDC gave 45 days plus three months till July 15 exhausting limit under IEGC Regulation 19(3)(a).

Premium Content Access

This content is available exclusively to our paid subscribers. Please login to enjoy full access. If you’re interested in subscribing to access our premium content, please contact us at support@omnicoreplus.com.

Related