Inox Green Energy Services lost grid connectivity for its 300 MW Gujarat wind project after failing deadlines. CERC upheld CTUIL’s disconnection, citing lack of financial closure and minimal progress despite extensions. Bank guarantees of ₹3.50 Crore were encashed. Delays were blamed on land, transmission, and pandemic issues, but the regulator rejected the plea.